Ergotem Projects

Project Description
Customer
Executional Period
Project Value
New Penitentiaries in Chania city in Crete: Construction of Building Complex, Building Works and Electromechanical and Security Installations
THEMIS CONSTRUCTIONS
2004-present
14.683.256,71 €
Engineering and Erection of New Health Centre at Heraklion city, Crete, Greece
MINISTRY OF HEALTH
2006-2008
11.060.775,20 €
New Judge Court Building in the city of Corfu Island, Greece
THEMIS CONSTRUCTIONS
2009-2012
7.396.199,04 €
Engineering, Supply, Manufacturing and Installation of a New Waste Water Treatment Centre for the Municipality of Elenos, Lefkada Island, Greece
MUNICIPALITY OF ELOMENOS
UNDER CONSTRUCTION
6.667.597,52 €
Engineering, Supply, Manufacturing and Installation of a New Waste Treatment Centre for Thriasio Area Attica, Greece
EYDAP
2009 – present
28.095.639,44 €
Engineering, Construction and Erection of two Steel Stucks for PPC’s Lesvos Islands Power Stations
PPC LESVOS ISLAND POWER STATION
1994
988.994,86 €
Construction and Erection of a complete Steam Boiler Unit with Auxiliary Boilers (2X3ton/HR) and Anchillaries, Stuck, Ducts, Pipe, Steel Structure and Civil Works
HEL.PE
2000 – 2001
1.013.190,10 €
Manufacturing of New Steam Boiler Plant parts Unit U5189
HEL.PE
2000 – 2001
301.895,52 €
Engineering Construction and Erection of two steel strucks for PPC’s Samos Island Power Stations, Greece
PPC SAMOS ISLAND POWER STATION
2002
2.390.650,74 €
Engineering and Erection of two Combined Cycle Power Units 27,95MWe at PPC’s Chania Crete Power Station, Greece
PPC SA
2003
582.000,00 €
Manufacturing, Erection and Installation of the Heat Exchanger Tower for TITAN Cement Factory, Thessaloniki, Greece
TITAN CEMENT COMPANY
2004
2.189.980,34 €
Supply and Installation of Equipment for the necessary modifications for the increase of District Heating Energy Supply from 67 MWth or 70MWth to 134MWth or 137MWth, for the District Heating System of Municipality of Kozani, Greece
PPC

AGIOS DIMITRIOS POWER STATION
2006 – 2007
2.333.000,00 €
Reduction of false air in the Burning of Boiler Unit III of SES MEGALOPOLIS, Greece
PPC

MEGALOPOLIS POWER STATION
2007 – 2009
4.615.500,00 €
Delivery, Installation and Testing of one ACC for Combined Cycle Power Plant of 435MWe of HERON II Power Station – Viotias SA, Greece
TERNA SA
2008 – 2009
1.600.000,00 €
Engineering Construction and Erection of Steel Stucks for PPC’s Power Stations in Lemnos, Samos and Syros Islands, Greece
PPC
2009 – 2011
2,694,000.00 €
Design, Supply, Installation and Duting into Operation of equipment for district Heating Power Supply 100MWth to the Municipality of Ptolemais for the Units III and IV of Kardia SES, Greece
PPC

KARDIA POWER STATION
UNDER CONSTRUCTION
4,480,000.00 €